| 研究生: |
邱培碩 Chiu, Pei-Shuo |
|---|---|
| 論文名稱: |
應用雷電路徑搜索演算法於配電變壓器巡檢及吊檢維護排程規劃之研究 Application of Lightning Search Algorithm to Inspection and Overhaul Maintenance Scheduling of Distribution Transformers |
| 指導教授: |
黃世杰
Huang, Shyh-Jier |
| 學位類別: |
碩士 Master |
| 系所名稱: |
電機資訊學院 - 電機工程學系 Department of Electrical Engineering |
| 論文出版年: | 2018 |
| 畢業學年度: | 106 |
| 語文別: | 中文 |
| 論文頁數: | 102 |
| 中文關鍵詞: | 雷電路徑搜索演算法 、配電變壓器 、排程規劃 |
| 外文關鍵詞: | Lightning search algorithm, distribution transformer, maintenance scheduling |
| 相關次數: | 點閱:70 下載:0 |
| 分享至: |
| 查詢本校圖書館目錄 查詢臺灣博碩士論文知識加值系統 勘誤回報 |
本論文提出雷電路徑搜索演算法應用於配電變壓器巡檢及吊檢維護排程規劃,研究主旨在於解決現行配電變壓器維護策略所面臨之挑戰,以提升配電變壓器維護效能,達到節省維護成本同時提升供電可靠度之成果。本文將配電變壓器維護成本、系統平均停電次數、系統平均停電時間以及絕緣壽命損失程度,統整考量建立數學模型,並考量鹽害及配電變壓器運轉狀況,然後輔以雷電路徑搜索演算法擬定配電變壓器維護排程策略,其中雷電路徑搜索演算法乃依據自然界之雷電搜索最佳閃絡路徑相關機制加以推導建模而成,有助於求解最佳化問題。而為驗證本文所提方法之可行性,本文利用包含不同個數配電變壓器之配電系統進行模擬測試,並與現行規劃策略及其他方法比較,經由測試結果可知,本文所提方法於配電變壓器維護排程規劃之應用,確已展現電力實務之高度應用潛力。
This thesis applies the lightning search algorithm to inspection and overhaul maintenance scheduling of distribution transformers, aiming at the improvement of transformer maintenance efficiency while cost reduction and high reliability of supplying-power are both concerned. By considering maintenance costs, system average interruption duration, system average interruption frequency, and insulation life loss percentage of transformer, the study first formulates mathematical models based on these objective functions, where salt corrosion and operation condition are also taken into considerations. This is followed by the application of lightning search algorithm in anticipation of reaching the maintenance scheduling decisions for distribution transformers. The algorithm applied in this study is developed based on mimicking the search of arcing path during the occurrence of lightning, by which it provides an optimization method for solving problems in a more effective manner. In order to verify the feasibility of this proposed method, the thesis applies this approach on a distribution system consisting of different numbers of distribution transformer. Test results of using the proposed methods are further compared with those of using existent strategies. Comparison outcomes support the proposed method for the distribution transformer maintenance scheduling study, exhibiting a high potential for practical power system applications.
[1] 台灣電力股份有限公司,「2016年台灣電力公司永續報告書」,民國一百零五年。
[2] Smart Grid Vision and Routemap, Department of Energy & Climate Change, United Kingdom, 2014.
[3] Y. T. Lin, W. F. Su, S. J. Huang, P. S. Chiu, K. T. Wu, and C. C. Wei, “A Study on Maintenance Management for Distribution Transformers of Electrical Power System”, Monthly Journal of Taipower’s Engineering, Vol. 836, pp.66- 76, April 2018.
[4] 「配電變壓器維護管理之研究」,台灣電力公司105年度研究計畫,105年12月。
[5] H. A. Aldhubaib and M. A. Salama, “A Novel Approach to Investigate the Effect of Maintenance on the Replacement Time for Transformers”, IEEE Transactions on Power Delivery, Vol. 29, No. 4, pp. 1603- 1612, August 2014.
[6] A. A. Jahromi, M. Parvania, F. Bouffard, and M. F. Firuzabad, “A Two-Stage Framewrok for Power Transformer Asset Maintenance Management – Part 1: Models and Formulations”, IEEE Transactions on Power System, Vol. 28, No. 2, pp. 1395-1403, May 2013.
[7] A. A. Jahromi, M. Parvania, F. Bouffard, and M. F. Firuzabad, “A Two-Stage Framewrok for Power Transformer Asset Maintenance Management – Part 2: Validation Results”, IEEE Transactions on Power System, Vol. 28, No. 2, pp. 1404-1413, May 2013.
[8] F. Campelo, L. S. Batista, R. H. C. Takahashi, H. E. P. Diniz, and E. G. Carrano, “Multicriteria Transformer Asset Management with Maintenance and Planning Perspectives”, IET Generation, Transmission and Distribution, Vol. 10, Iss. 9, pp. 2087- 2097, 2016.
[9] K. Kolsal and A. Ozdemir, “Improved Transformer Maintenance Plan for Reliability Centered Asset Management of Power Transmission System”, IET Generation, Transmission and Distribution, Vol. 10, Iss. 8, pp. 1976-1983, 2016.
[10] S. K. Abeygunawardane, P. Jirutitijaroen, and H. Xu, “Adaptive Maintenance Polices for Aging Devices Using a Markov Decision Process”, IEEE Transactions on Power Systems, Vol. 28, No. 3, pp. 3194- 3203, August 2013.
[11] J. Zhong, W. Li, C. Wang, J. Yu, and R. Xu, “Determining Optimal Inspection Intervals in Maintenance Considering Equipment Aging Faiure”, IEEE Transactions on Power Systems, Vol. 32, No. 2, pp. 1474-1482, March 2017.
[12] F. Yang, C. M. Kwan, and C. S. Chang, “Multiobjective Evolutionary Optimization of Maintenance Using Decision-Varying Markov Model”, IEEE Transactions on Power System, Vol. 23, No. 3, pp. 1328- 1335, August 2008.
[13] F. Yang and C. S. Chang, “Optimisation of Maintenance Schedules and Extents for Composite Power Systems Using Multi-Objective Evolutionaty Algorithm”, IET Generation, Transmission & Distribution, Vol. 3, Iss. 10, pp. 930-940, June 2009.
[14] Y. Yumbe, T. Hasegawa, and N. Furukawa, “Optimization Method for Inspection Scheduling of Power Distribution Facilities”, IEEE Transactions on Power Delivery, Vol. 28, No. 3, pp. 1558- 1565, July 2013.
[15] Y. Yumbe, M. Miyakoshi, M. Kondo, T. Arao, and N. Furukawa, “Evaluation of Optimization Method for Inspection Scheduling of Power Distribution Facilities Using Maintenance Data Accumulated by Power Utility”, IEEE Transactions on Power Delivery, Vol. 32, No. 2, pp. 696- 702, April 2017.
[16] A. D. Janjic and D. S. Popovic, “Selective Maintenance Schedule of Distribution Networks Based on Risk Management Approach”, IEEE Transactions on Power System, Vol. 22, No. 2, pp. 597- 604, May 2007.
[17] A. A. Jahromi, M. F. Firuzabad, and E. Abbasi, “An Efficient Mixed-Integer Linear Formulation for Long-Term Overhead Lines Maintenance Scheduling in Power Distribution Systems”, IEEE Transactions on Power Delivery, Vol. 24, No. 4, pp. 2043- 2053, October 2009.
[18] A. Moradkhani, M. R. Haghifam, and M. Mohammadzadeh, “Failure Rate Modeling of Electric Distribution Overhead Lines Considering Preventive Maintenance”, IET Generation, Transmission and Distribution, Vol. 8, Iss. 6, pp. 1028- 1038, 2014.
[19] V. Aravinthan and Ward Jewell, “Optimized Maintenance Scheduling for Budget-Constrained Distribution Utility”, IEEE Transactions on Smart Grid, Vol. 4, No. 4, pp. 2328- 2338, December 2013.
[20] H. Shareef, A. A. Ibrahim, and A. H. Mutlag, “Lightening Search Algorithm”, Applied Soft Computing, Vol. 36, pp. 315- 333, November 2015.
[21] M. A. Hannan, J. A. Ali, A. Mohamed, U. A. U. Amirulddin, N. M. L. Tan, and M. N. Uddin, “Quantum-Behaved Lightning Search Algorithm to Improve Indirect Field-Oriented Fuzzy-PI Control for IM Drive”, Industry Applications Society Annual Meeting, Cincinnati, USA, October 2017.
[22] 「普通型桿上變壓器」,台灣電力公司材料標準,101年8月。
[23] 「密封型桿上變壓器」,台灣電力公司材料標準,99年7月。
[24] 「亭置式變壓器」,台灣電力公司材料標準,100年8月。
[25] 「配電技術手冊(三)運轉維護篇」,台灣電力公司配電處,2014年11月。
[26] 「配電技術手冊(十七)配電設備檢修」,台灣電力公司業務處,98年8月。
[27] C. Sumereder, “Statistical Lifetime of Hydro Generators and Failure Analysis”, IEEE Transactions on Dielectrics and Electrical Insulation, vol. 15, no. 3, pp. 678-685, June 2008.
[28] J. B. Ali, B. C. Morello, L. Saidi, and F. Fnaiech, “Accurate Bearing Remaining Useful Life Prediction Based on Weibull Distribution and Artificial Neural Network”, Mechanical Systems and Signal Processing, Vol. 56-57, pp.150-172, May 2015.
[29] J. Zhang, T. Zhou, H. Wu, W. Wu, and J. Ren, “Constant Step Stress Accelerated Life Test of White OLED Under Weibull Distribution Case”, IEEE Transactions on Electron Devices, Vol. 59, No. 3, pp. 715-720, March 2012.
[30] T. Tsuboi, J. Takami, S. Okabe, K. Inami, and K. Aono, “Weibull Parameter of Oil-Immersed Transformer to Evaluate Insulation Reliability on Temporary Overvoltage," IEEE Transactions on Dielectrics and Electrical Insulation, Vol. 17, No. 6, pp. 1863-1868, December 2010.
[31] T. Tsuboi, J. Takami, S. Okabe, K. Inami, and K. Aono, “Aging Effect on Insulation Reliability Evaluation with Weibull Distribution for Oil-Immersed Transformers,” IEEE Transactions on Dielectrics and Electrical Insulation, Vol. 17, No. 6, pp. 1869-1876, December 2010.
[32] S. J. Almalki and S. Nadarajah, “A New Discrete Modified Weibull Distribution”, IEEE Transactions on Reliability, Vol. 63, No. 1, pp. 68-80, March 2014.
[33] S. Okabe, G. Ueta, and T. Tsuboi, “Investigation of Aging Degradation Status of Insulating Elements in Oil-immersed Transformer and Its Diagnostic Method Based on Field Measurement Data”, IEEE Transactions on Dielectrics and Electrical Insulation, Vol. 20, Iss. 1, pp. 346-355, February 2013.
[34] A. K. Mehta, R. Naresh, and S. Chauhan, “Development of a Novel Dual Temperature Model for Insulation Aging in Oil immersed Transformers”, IEEE Transactions on Dielectrics and Electrical Insulation, Vol. 22, Iss. 5, pp. 2723-2735, November 2015.
[35] K. T. Muthanna, A. Sarkar, K. Das, and K. Waldner, “Transformer Insulation Life Assessment,” IEEE Transactions on Power Delivery, Vol. 21, No. 1, pp. 150-156, January 2006.
[36] IEEE Std. C57.91-2011, “IEEE Guide for Loading Mineral Oil Immersed Transformers and Step-Voltage Regulators,” March 2012.
[37] 「台電輸電線路礙子等效鹽分附著量分布圖」,台灣電力公司綜合研究所。
[38] M. Hinow and M. Mevissen, “Substation Maintenance Strategy Adaption for Life-Cycle Cost Reduction Using Genetic Algorithm”, IEEE Transactions on Power Delivery, Vol. 26, No. 1, pp. 197-204, January 2011.
[39] K. Suresh and N. Kumarappan, “Generation Maintenance Scheduling Using Improved Binary Particle Swarm Optimisation Considering Aging Failures”, IET Generation, Transmission & Distribution, Vol.7, Iss. 10, pp. 1072- 1086, October 2013.
[40] American National Standard, “Standard for Maintenance Testing Specifications for Electrical Power Distribution Equipment and Systems”, ANSI/NETA MTS-2011.
[41] 受変電設備保守点检の要点,日本電機工業會,2005年5月。
[42] O. Kwon, B. Jung, J. Joung and D. Kim, “Review and Application and Diagnosis Method for 22.9kV-y Distribution Systems”, 2012 IEEE International Conference on Condition Motinoring and Diagnosis, Bali, Indonisia , pp. 802-804. September 2010.
校內:2023-07-23公開