簡易檢索 / 詳目顯示

研究生: 賈司帝
Castillo, Mario
論文名稱: 應用BIM 於營建物料管理之材料運送及交貨提前時間分析
Applying BIM to Construction Material Management-A Case Study on Material Delivery & Lead Time Analysis
指導教授: 馮重偉
Feng, Chung-Wei
學位類別: 碩士
Master
系所名稱: 工學院 - 土木工程學系
Department of Civil Engineering
論文出版年: 2014
畢業學年度: 102
語文別: 英文
論文頁數: 102
外文關鍵詞: BIM, Work package, Lead time, linear schedule, Precedence diagram
相關次數: 點閱:91下載:1
分享至:
查詢本校圖書館目錄 查詢臺灣博碩士論文知識加值系統 勘誤回報
  • Good management in materials delivery can improve the project delivery, it can avoid uncertainties and it can reduce project cost. However, if we don’t have the necessary information it would be difficult to enhance the material delivery and to the materials management in general. Information such as the suppliers’ production time or the material delivery time, are some examples of the data that many constructions companies do not manage, and do not think to develop; this is why this research aims to enhances the constraints in materials delivery.
    Others researchers have focused only on the lead time improvement of the precast production. They have developed several considerations in order to calculate the lead time in precast production, and they have created work packages that enhance the activities during the construction.
    This research got the ideas of the previous works and their accomplished. The approach of this research is to develop a work package that enhances the suppliers’ production time by gathering the necessary information for the development of the product and by knowing the lead time of our suppliers.
    This research implements the benefits of the Building Information Model (BIM) to enhance the information needed in the work package, and calculates the lead time of the different materials. Applying the Building Information Model (BIM) helps the manager to calculate and introduce the lead time inside the schedule of the BIM model. Also, we can benefit from the linear schedule and precedence diagram that BIM offers us, and we can improve the information that we need to develop the work packages and accomplish the proposed project model. This research developed a case study that demonstrates the benefit to implement the different methods in the framework, to reduce time and cost in the construction project.

    ABSTRACT..................................I ACKNOWLEDGEMENTS......................... III TABLES OF FIGURE......................... IX LIST OF TABLES........................... XI Chapter 1. INTRODUCTION ................. 1 1.1 Background........................... 1 1.2 Motivation........................... 2 1.3 Objectives........................... 3 1.4 Research procedure................... 4 1.5 Thesis structure..................... 4 Chapter 2. LITERATURE REVIEW............. 6 2.1 Problem statement.................... 6 2.2 Relationship between contractor and supplier................................. 8 2.2.1 Materials delivery................. 8 2.2.2 The importance of detail information.............................. 9 2.3 Benefits of the Work package (WP)..................................... 10 2.4 Building Information Model (BIM)..... 11 2.4.1 Project Delivery Methods & BIM for Construction Managers ................................ 12 2.4.2 BIM in Construction Management..... 14 2.4.3 Visualization...................... 15 2.4.4 Prefabrication and fabrication..... 15 2.5 Building Information Modeling (BIM) application .......................... 16 2.6 BIM-implementation Facilities Management............................... 19 2.7 Project Schedule and Lead time in materials delivery ...............................21 2.7.1 Last planner system ............... 23 2.7.2 Lead time of materials ............ 24 2.7.3 Precedence diagram ................ 25 2.7.4 Linear scheduling.................. 26 2.8 Summary ............................. 27 Chapter 3 METHODOLOGY ................... 29 3.1 Fish bone diagram analysis........... 29 3.2 Work package (WP).................... 31 3.3 Building Information Model (BIM).................................... 32 3.4 Lead time estimation model (LTEM).... 33 3.5 Last Planner system.................. 34 3.6 Precedence Diagram and linear scheduling............................... 35 Chapter 4. FRAMEWORK FOR APPLYING BIM TO CONSTRUCTION MATERIAL MANAGEMENT ..................... 37 4.1 Scope Definition..................... 37 4.2 Framework Key Assumption............. 41 4.3 Framework Implementation Requirements 42 4.3.1 Define type of project............. 42 4.3.2 Identify stakeholders ............. 42 4.3.3 Stakeholder’s needs analysis....... 43 4.3.4 Lead time base equation and analysis................................. 49 4.3.5 Lead time variability.............. 49 4.3.6 Lead time equation requirements............................. 50 4.4 Procedure of the Framework .......... 52 4.4.1 Materials Demand and Specification..52 4.4.2 Preliminary Building Information Model (BIM) model......................... 52 4.4.3 Lead time calculation.............. 53 4.4.4 Develop the project schedule...................... 59 4.5 Element of the Framework............. 61 4.5.1 Create the Work package............ 61 Chapter 5: CASE STUDY.................... 65 5.1 Project Overview..................... 65 5.2 Framework Implementation............. 67 5.2.1 Identify our stakeholder and requirements.......... 67 5.2.2 Develop the preliminary Building Information Model (BIM) ............. 69 5.2.3 Lead time calculation ............. 72 5.2.4 Develop the BIM.................... 77 5.2.5 Create the Work package............ 81 5.3 Results verification ................ 83 5.3.1 Benefits in other areas............ 85 Chapter 6.CONCLUSION AND SUGGESTIONS..... 86 6.1 Conclusions.......................... 86 6.2 Implication for future research...... 87 REFERENCES .............................. 89

    1. A. Eldosouky, E. Elbeltagi, T. Hegazy, “Dynamic layout of construction temporary facilities considering safety”. Journal of Construction Engineering and Management. (2004)
    2. Albert Humphrey, “SWOT analysis”, Strategic management, Stanford Research Institute. (1970s)
    3. Affari Group, “Containers specifications”, www.affari.com.ar/conttt.htm. (2011)
    4. Alibaba Group, “Supplier’s information trading companies”, http://www.alibaba.com/. (2014)
    5. Alireza Khalili1 and David K. H. Chua, M.ASCE, “IFC-Based Framework to Move beyond Individual Building Elements toward Configuring a Higher Level of Prefabrication”. Journal of computing in civil engineering. (May 2013)
    6. Alves, T.C.L., Tommelein, I.D., “Buffering and batching practices in the HVAC Industry”. Proceedings of the 11th Conference of the International Group for Lean Construction. Virginia Tech, Blacksburg, Virginia. (22–24 July, 2003).
    7. Ballard, G., “The Last Planner System of production control”. School of Civil Engineering, Faculty of Engineering, the University of Birmingham. (2000)
    8. Benn Lawson, Sinéad Roden, “Developing Social Capital in Buyer-Supplier Relationships: The Contingent Effect of Relationship- Specific Adaptations”. Int. J. Production Economics. PROECO5671. (7 January 2014).
    9. Burcin Becerik-Gerber, A.M.ASCE, Farrokh Jazizadeh; Nan Li and Gulben Calis, “Application Areas and Data Requirements for BIM-Enabled Facilities Management”. Journal of Construction Engineering and Management. Vol. 138, No. 3. (March 1, 2012).
    10. Burcu Akinci, Lieyun Ding and Ying Zhou, “Building Information Modeling (BIM) application framework: The process of expanding from 3D to computable nD”. Automation in Construction. (14 April 2014)
    11. Chien-Ho Ko., “Arranging precast production schedules using demand variability”. Proceedings for the 20th Annual Conference of the International Group for Lean Construction. (2010)
    12. Daniel W. Halpin, “Construction management”, Bolivar A senior international student version, Purdue University, third edition. (August 31st 2005)
    13. D.R. Riley, J.I. Messner, H.R. Thomas., “Fundamental principles of site materials management”, Journal of Construction Engineering and Management. 131 (7) (2005) 808–815. (2005).
    14. Eric W.T. Ngai b., Junyi Chai a, James N.K. Liu., “Application of decision-making techniques in supplier selection: A systematic review of literature”. Expert Systems with Applications. 40 (2013) 3872–3885. (2013)
    15. Gregory Howell, M.ASCE; Simon M. Hsiang; and Min Liu, A.M.ASCE4 Marion M. Russell1, “Application of Time Buffers to Construction Project Task Durations”. American Society of Civil Engineers. DOI: 10.1061/ (ASCE) CO.1943-7862.0000735. (2013).
    16. H.P. Tserng, Y.L. Samuel, L. Sherman, “Developing a resource supply chain planning system for construction projects”, Journal of Construction Engineering and Management. 132 (4) (2006) 393–407. (2006).
    17. H.R. Thomas, M.J. Horman, “Role of inventory buffers in construction labor performance”. Journal of Construction Engineering and Management. ASCE 131 (7) (2005) 834–843. (2005).
    18. Kaoru Ishikawa, “Ishikawa fish bone analysis”. (1968).
    19. Jae G. Jeong, Makarand Hastak, M.ASCE; Matt Syal, M.ASCE; and Taehoon Hong, A.M.ASCE, “Framework of Manufacturer and Supplier Relationship in the Manufactured Housing Industry”. American Society of Civil Engineers. DOI: 10.1061/ (ASCE) ME.1943-5479.0000164. (2013).
    20. Jimmie W. Hinze, “Construction planning and scheduling”, third edition, Pearson international edition. (2012)
    21. José Luis Gómez, “Table of materials specific weights” (Spanish version), http://www.lorenzoservidor.com.ar/facu01/tablas/especif.htm
    22. Matthias Schmidt Peter Nyhuis, Sebastian Beck, “Model-based logistic controlling of converging material flows”. Institute of Production Systems and Logistics, Leibniz Universitaet Hannover, An der Universitaet 2, 30823 Garbsen, Germany. CIRP Annals - Manufacturing Technology. 62 (2013) 431–434. (2013)
    23. Mehmet F. Hergunsel. “Thesis Benefits of building information modeling for construction managers and BIM based scheduling”. Worcester Polytechnic Institute, Master of Science in Civil Engineering. (May 2011)
    24. National Institute of Building Sciences Project Planning a program WBDG (whole building design), “Delivery and Controls”. (June 11th 2012). www.wbdg.org/project/pm.php.
    25. Seunghee Kang and Youngsoo Jung, A.M.ASCE, “Knowledge-Based Standard Progress Measurement for Integrated Cost and Schedule Performance Control”. Journal of Construction Engineering and Management. Vol. 133, No. 1, DOI: 10.1061/ (ASCE) 0733-9364(2007)133:1(10). (January 1st, 2007).

    下載圖示 校內:立即公開
    校外:立即公開
    QR CODE